Data Center Power: Supply Side and Demand Side
AI has overnight turned electricity into the most expensive bottleneck in data centers. For the past decade this industry obsessed over bandwidth, latency, and PUE; now the top question is blunter — where does the power come from, is there enough of it, and when will it actually be available.
Following that question, I worked through a macro survey from both the supply side (where power comes from) and the demand side (where power goes), and I’m writing it up as a stage-gated research note.

Supply Side: Where the Power Comes From
Data center power supply can be divided into two modes, delineated by the utility meter.
Front-of-the-Meter: Direct Connection to the Utility Grid
Power comes from the local grid and is paid for by usage — this is still the dominant model. As recently as a year ago, facilities that actually relied on on-site generation as their primary power source numbered only about 13%, meaning roughly 87% still depended primarily on the grid; a Bloom Energy industry survey of around 100 decision-makers projects that the on-site share will rise to about 38% by 2030, with roughly 60% of data centers still grid-dependent at that point[1].
Worth calling out separately is the “nuclear PPA” trend that has been generating significant buzz over the past two years:
- In 2024, Microsoft signed a 20-year agreement with Constellation to restart the shuttered Three Mile Island Unit 1 — renamed the Crane Clean Energy Center — delivering its full 835 MW exclusively to Microsoft AI data centers, with grid connection targeted for 2027–2028[2].
- In June 2025, Meta signed a 20-year deal with Constellation to take the entire 1,121 MW output of the Clinton Power Station in Illinois, beginning in June 2027[3].

One thing worth clarifying: these “nuclear + AI” headline deals are structurally still front-of-the-meter — the data center does not own the reactor, the arrangement is a PPA (Power Purchase Agreement), and power still travels over the grid. Truly behind-the-meter nuclear means small modular reactors (SMRs) located within the data center campus itself, and that remains essentially in the planning and first-unit construction phase.
Behind-the-Meter: Data Centers Building Their Own Generation
Generation equipment is installed on the data center’s own side of the meter, and power is consumed directly without passing through a utility meter. This is the fastest-growing segment right now, and the core driver is simple — grid interconnection queues often mean waiting several years, making on-site build-out the fastest path to meeting project timelines[1].
Behind-the-meter on-site solutions, arranged roughly by deployment speed and scale, span a spectrum like this:
| Solution | Deployment Timeline | Characteristics | Representative Players |
|---|---|---|---|
| Fuel cells | Fastest (~90 days) | Most agile, smallest footprint, near-zero noise/NOx, suited for rapid emergency deployment | Bloom Energy (leader); FuelCell Energy, Plug Power, Ballard, Doosan |
| Small gas turbines / reciprocating engines | ~12–24 months | Solid and reliable, suited for mid-scale | GE Vernova (LM2500/LM6000), Caterpillar, Cummins; Solaris (leasing) |
| Large gas turbines | New orders queued to ~2028–2030 | Highest per-unit capacity, most economical at scale | GE Vernova, Mitsubishi Power, Siemens Energy |
| Nuclear (incl. SMR) | Restart ~3 years / SMR post-2030 | Largest scale, most stable, cleanest, long-term solution | Operators: Constellation, Vistra; SMR developers: Kairos, NuScale, Oklo |
| Energy storage | Supplemental | Peak shaving, load smoothing | Tesla (Megapack), Fluence |
Fuel Cells: Fastest and Most Flexible
Fuel cells play the role of “speed-first option.” In Bloom Energy’s partnership with Oracle, the target was on-site data-center-scale power delivery in 90 days — in practice, the first batch of modules was delivered in just 55 days[4]. The physical form factor is a set of shipping-container-sized modules that can be combined into installations ranging from 20 MW to 500 MW+, running on natural gas, biogas, or hydrogen, with availability of 99.9%–99.999%[5].
The trade-off is a per-watt capital cost roughly 10%–15% higher than small gas turbines, but in islanded microgrid deployments requiring 99.9% availability, that gap is offset by the over-build cost gas turbines incur to maintain standby redundancy[6].

Gas Turbines: The Backbone of Large-Scale Behind-the-Meter Power
What truly underpins large-scale behind-the-meter deployments is gas turbines. GE Vernova’s LM2500 has now surpassed 2,100 cumulative deliveries and 75 million operating hours; the LM6000 has more than 1,200 deliveries and 60 million operating hours, and can synchronize to grid within 5 minutes of startup[7]. Both are aeroderivative models — derived directly from commercial aviation jet engines — which makes them rugged, reliable, and backed by a mature maintenance ecosystem.

That said, order books at large gas turbine manufacturers are already filled out to 2028–2030, so new data centers hoping to use this path simply cannot afford the wait.
Nuclear and SMR: The Long-Term Optimal Solution, but Still a Distant Horizon
SMRs are the central narrative for “behind-the-meter nuclear”: shrink a reactor into factory-manufactured modular units, assemble them on-site, and locate them directly within the data center campus. The most aggressive plan — Oklo’s Aurora — aims for its first unit to go online in 2027–2028, but the mainstream estimate is that the first commercial SMRs will enter data center service power around 2030; NuScale has signed a 6 GW deal with TVA with a target of power generation from the first plant by 2030; Kairos’s Hermes-2 molten-salt reactor is also targeting 50 MW for TVA in 2030[8].

Business Model: Short Hardware Tail, Long Service Tail
Behind-the-meter equipment vendors typically operate on a model of “one-time hardware sale + 15–20 year long-term service contract.” Taking Bloom Energy’s backlog as of end-2025 as an example: product backlog roughly $6 billion, service backlog roughly $14 billion, totaling roughly $20 billion — a 3:7 hardware-to-service split, with services forming the much longer tail[9].
This model is structurally identical to the playbook of aviation engine manufacturers (GE, Rolls-Royce) and industrial gas companies (Air Liquide): deploy the expensive hardware first, then collect maintenance, spare parts, and fuel contract revenue over the following two to three decades — long-term contracts lock in customers, and service cash flows are smooth and counter-cyclical.
Demand Side: Where the Power Goes
Having covered the supply side, the next question is: once power enters the data center, exactly where does it go?
Both Epoch AI and American Compute have broken this down using NVIDIA’s official GB200 reference architecture. Taking a reference AI data center of approximately 171 MW (NVIDIA GB200 NVL72 architecture), the approximate power share by module is as follows[10][11]:
| Module | Share |
|---|---|
| GPUs | ~40% |
| Other server components (CPU, memory, NVLink, PSU losses, etc.) | ~22% |
| Cooling + power distribution | ~29% |
| Networking equipment | ~9% |
The 29% for cooling is based on air cooling; switching to direct liquid cooling can bring this below 15%[10].
GPUs are the dominant power consumer by far: H100 700W → B200 1,000W → B300 1,400W — each generation more demanding than the last. Eight GPUs in a single chassis, without accounting for CPU or networking, already draws 11.2 kW; starting with the B300, liquid cooling is not optional[12]. For comparison, a single Intel/AMD server CPU draws roughly 300W — not remotely in the same league.

Metrics: From PUE Toward Tokens-per-Watt
PUE (Power Usage Effectiveness) = total facility power ÷ IT equipment power, closer to 1.0 is better. This metric has been in use for nearly two decades; the global industry weighted average has hovered around 1.54 for six years with essentially no movement. Top operators, however, can push it to extremes — Google’s trailing twelve-month PUE across its global data center fleet in 2024 was 1.09[13][14].
Water and carbon have their own parallel metrics: WUE (water) and CUE (carbon), with the same logic as PUE, just different denominators.
Genuinely new in the AI era is a shift in metrics from “energy consumption efficiency” toward “compute output efficiency”:
- Tokens per Watt: how many tokens can be generated per watt of power — this measures actual compute output rather than bare energy consumption.
- Rack power density (kW/rack): the global average remains only 7.5 kW, but AI training racks routinely run 30–120 kW — an order of magnitude higher. In the Uptime Institute survey, only one in eight facilities had any racks in the 30–59 kW range, and those capable of sustaining 100 kW+ reliably remain a small minority[13].
The rack density gap is fundamentally the question of whether legacy general-purpose cloud infrastructure can physically accommodate the next generation of GPUs — many older data centers are not short on power per se, but their cooling is inadequate, their power distribution was never designed for it, and their per-rack limits simply cannot reach those levels.
Summary
- Supply side: front-of-the-meter (grid) still dominates at roughly 70–80%, while behind-the-meter (on-site) is the fastest-growing segment. Within that segment, the deployment speed spectrum runs from fuel cells → small gas turbines → large gas turbines → nuclear, integrated with storage. Vendor business models follow a “hardware + long-term services” structure where services are the larger share (roughly 3:7). Front-of-the-meter nuclear PPAs are the shortcut for hyperscalers; behind-the-meter SMR is the long-term narrative — but real deployment is at least several years out, around 2030.
- Demand side: GPUs ~40%, other server components ~22%, cooling + power distribution ~29%, networking ~9%. Metrics are evolving from the legacy generation of PUE / WUE / CUE toward tokens-per-watt and rack power density — those are the true “capacity metrics” that matter in the AI era.
In the next phase I want to dig separately into several threads: where the actual bottlenecks are in gas turbine production capacity, how large a real market share Bloom Energy can capture in this cycle, and whether the SMR cost curve can ultimately compete with gas — all left for future notes.
References — sources
- Bloom Energy. 2025 Data Center Power Report — Onsite Generation Expected to Fully Power 27% of Data Center Facilities by 2030, 2025. bloomenergy.com/news/…35-gw-energy-gap-by-2030
- Constellation Energy. Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid, Sep 2024. constellationenergy.com/news/2024/Crane-Clean-Energy-Center
- Constellation Energy. Constellation, Meta Sign 20-Year Deal for Clean, Reliable Nuclear Energy in Illinois, Jun 2025. constellationenergy.com/newsroom/2025/Meta-Clinton
- Power Engineering. Oracle, Bloom Energy strike data center power deal, 2025. power-eng.com/onsite-power/oracle-bloom-energy-strike-data-center-power-deal
- Bloom Energy. Reliable Data Center Power Solutions. bloomenergy.com/industries/data-center-power
- Seeking Alpha. Bloom Energy: Solving The AI Data Center Power Bottleneck, 2026. seekingalpha.com/article/4862022-bloom-energy-solving-the-ai-data-center-power-bottleneck
- GE Vernova. LM2500 & LM2500XPRESS Gas Turbines and LM6000 Aeroderivative Gas Turbine. gevernova.com/lm2500 · gevernova.com/lm6000
- Introl. SMR Nuclear Power for AI Data Centers: Feasibility and Implementation Timeline, 2026. introl.com/blog/smr-nuclear-power-ai-data-centers-implementation
- Bloom Energy. Q4 and Full Year 2025 Financial Results, Feb 2026. investor.bloomenergy.com/press-releases/Q4-2025
- Epoch AI. GPUs account for about 40% of power usage in AI data centers. epoch.ai/data-insights/gpus-power-usage-in-ai-data-centers
- American Compute. The Power Budget of an AI Data Center. amcompute.com/blog/the-power-budget-of-an-ai-data-center
- Introl. NVIDIA Blackwell Ultra and B300: Infrastructure Requirements, 2025. introl.com/blog/nvidia-blackwell-ultra-b300-infrastructure-requirements-2025; see also NVIDIA’s official H100 and GB200 NVL72 pages.
- Uptime Institute. Global Data Center Survey 2025. uptimeinstitute.com/resources/global-data-center-survey-results-2025
- Google. Power Usage Effectiveness — Google Data Centers. datacenters.google/efficiency